For a stakeholder with low interest and high power, the project manager should:

For a stakeholder with low interest and high power, the project manager should:

A.Monitor the stakeholder.

B.Manage the stakeholder closely.

C.Keep the stakeholder satisfied.

D.Keep the stakeholder informed.