Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

A.-8000

B.-2000

C.2000

D.8000