9
When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:
A.divided among each of the phases or subprojects.
B.repeated for each of the phases or subprojects.
C.linked to specific
phases or subprojects.
D.integrated for specific phases or subprojects.