At the start of a typical project life cycle, costs are:

A.
low, peak as work is carried out, and drop as the project nears the end.
B.
low, become steady as work is carried out, and increase as the project nears the end.
C.
high, drop as work is carried out, and increase as the project nears the end.
D.
high, become low as work is carried out, and drop as the project nears the end.
The correct answer is A. low, peak as work is carried out, and drop as the project nears the end. – Pgs. 39 & 40 of PMBok 5th Ed.
0
0
yes, according to PMBOK5 the correct answer is “At the start of a typical project life cycle, costs are low, peak as work is carried out, and drop as the project nears the end.”