What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost
(AC) is $150, and the earned value (EV) is $50?
A.
0.50
B.
0.67
C.
1.50
D.
2.00
You must be logged in to post a comment.
spi=ev/pv