PrepAway - Latest Free Exam Questions & Answers

which of the following is the best answer?

Scenario: Zephyr Enterprises
Please read this scenario prior to answering the question

Zephyr Enterprises specializes in the development of wind turbine blades for use in large-scale
commercial wind energy production systems. Zephyr has manufacturing facilities located in Palm
Springs, California, Omaha, Nebraska, and Winnipeg, Ontario. Each of these plants supplies a
different manufacturer that builds and sells complete systems. The turbine blades are custom
engineered to meet each manufacturers design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics.
However, recent improvements in composite materials, coupled with enhanced automated methods
for precision application of materials during the molding process, have led to significant reduction in
weight, increase in strength, and greatly improved blade longevity. Zephyr has pioneered the
development of a proprietary automated process for continuous extrusion of the turbine blades.
Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
Zephyr has a mature Enterprise Architecture organization that is supported by a cross-functional
Architecture Review Board. The Chief Information Officer and the Chief Operating Officer co-sponsor
the Enterprise Architecture program.
Zephyr has used TOGAF and its Architecture Development Method (ADM) to develop its automated
manufacturing processes and systems that are used to design, manufacture, and test the blade
assemblies. They have recently updated to TOGAF 9 and have adapted the Zephyr Enterprise
Architecture to closely follow the TOGAF 9 framework. All of Zephyrs IT architects have been trained
and certified on TOGAF 9.Recently, an architecture project was completed that defined a standard
approach for controlling the Automated Test System that is used at each plant to perform final
quality assurance tests on each completed blade assembly. The Manufacturing Architecture Board
approved the plan for immediate implementation at each plant.
An Architecture Contract was developed that detailed the work needed to implement and deploy
the new Automated Test System controller. The Chief Engineer, sponsor of the activity, has
expressed concern that a uniform process be employed at each site to ensure consistency.
Refer to the Zephyr Enterprises Scenario:
You have been assigned by the Lead Architect for the Automated Test System controller project to
conduct Compliance Assessments at each manufacturing plant.
During the course of the assessment at the Omaha plant, you discover that the Distributed Data
Acquisition System they have purchased uses a proprietary Remote Procedure Call (RPC) that utilizes
kernel mode threads instead of the user mode threads that are specified in the Architecture
Definition Document. In all other respects, the system meets the requirements stated in the
Architecture Definition Document and seems to perform correctly.
You have been asked to describe the compliance of this system for the final report.
Based on TOGAF 9, which of the following is the best answer?

PrepAway - Latest Free Exam Questions & Answers

A.
You observe that all of the features in the Architecture Definition Document have been
implemented in accordance with the specification, except for the RPC mechanism. Your
recommendation is that the system be described as conformant.

B.
You observe that the system has many features in common with the Architecture Definition
Document, and those features have been implemented in accordance with the specification.
However, you note that the RPC mechanism has been implemented using features that are not
covered by the specification. Your recommendation is that the system be described as consistent.

C.
You observe that the implementation of the RPC mechanism has no features in common with the
Architecture Definition Document, therefore the question of its conformance should not be
considered. Your recommendation is that the system be described as consistent.

D.
You observe that the system meets most of the requirements stated in the Architecture Definition
Document and appears to work correctly. However, you note that the RPC mechanism has not been
implemented according to the specification. Your recommendation is that the system be described
as non-conformant.

4 Comments on “which of the following is the best answer?

  1. Ali says:

    Ans: D – Non-Conformant
    48.2 Terminology: The Meaning of Architecture Compliance
    Figure 48-1 Levels of Architecture Conformance




    0



    0
  2. Punjab says:

    From Section 48.2
    “Consistent: The implementation has some features in common with the architecture specification, and those common features are implemented in accordance with the specification. However, some features in the architecture specification are not implemented, and the implementation has other features that are not covered by the specification”.

    “Conformant: All the features in the architecture specification are implemented in accordance with the specification, but some more features are implemented that are not in accordance with it”.

    “Non-conformant: Any of the above in which some features in the architecture specification are implemented not in accordance with the specification. ”

    The key here is that the feature is indeed implemented, and works correctly, but it is not in accordance with the specification.

    Therefore option D is the answer.




    1



    0

Leave a Reply

Your email address will not be published. Required fields are marked *