PrepAway - Latest Free Exam Questions & Answers

You need to track task-level airfare costs that do not depend on the amount of work or duration of a task

You track all costs on your project. You need to track task-level airfare costs that do not
depend on the amount of work or duration of a task. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Use a work type resource.

B.
Create a custom field and capture travel costs at the project level.

C.
Use a budget resource.

D.
Use a cost type resource.

Explanation: