You need to set the default constraint type for all new tasks to As Late As Possible

You need to set the default constraint type for all new tasks to As Late As Possible. What
should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Select all tasks, and then click Layout.

B.
In the Options dialog box, enable the New Tasks are effort driven check box.

C.
Select all tasks, and then set the constraint type to As Late As Possible.

D.
In the Project Information window, from the Schedule From drop-down list box, select
Project Finish Date.