You need to ensure that the change in John¡¯s working time is reflected in the project schedule

Five resources work full time on the project. Standard working hours are eight hours a day
from Monday through Friday. John, a team member, asks to take Thursday off from work.
He will work on Saturday to adjust this time. You need to ensure that the change in John¡¯s
working time is reflected in the project schedule. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Update the resource calendar for John by making Thursday as a non-working day and
Saturday as a working day.

B.
In the Resource Information window for John, select the inactive option for Thursday and
cancel the selection of the inactive option for Saturday.

C.
Update the project calendar for John by making Thursday as a non-working day and
Saturday as a working day.

D.
In the Resource Information window for John, change John¡¯s availability by modifying
the Available From and Available To dates for Thursday to 0 percent and for Saturday to 100
percent.