How should you configure Task 2?

You have two dependent tasks named Task 1 and Task 2. Task 1 is the predecessor for
Task 2. You need to ensure that when the duration of Task 1 changes, the scheduled start
date for Task 2 does not change automatically. How should you configure Task 2?

PrepAway - Latest Free Exam Questions & Answers

A.
Set the task type to Fixed Duration.

B.
Set the lag to two elapsed days (2ed).

C.
Set the constraint type to Start No Earlier Than.

D.
Set the schedule mode to Manually Scheduled.

Explanation: