PrepAway - Latest Free Exam Questions & Answers

You need to be able to identify a possible resolution for the over-allocated resources

You are reviewing the task details of your project. You receive the following warning
message:
“This task has resources assigned which are over-allocated.”
You need to be able to identify a possible resolution for the over-allocated resources.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Change the task type to Fixed Work, and then recalculate the project.

B.
Change the task type to Fixed Units, and then recalculate the project.

C.
Increase the task duration values for the task.

D.
Use the Task Inspector tool.

E.
Set the Level Assignments flag to Yes for the task, and then recalculate the schedule.


Leave a Reply