Exam 70-178: Microsoft Project 2010, Managing Projects

You need to move the section to another phase of the project

A section of your project contains only a summary task along with four subtasks and a
milestone. You discover that the section is located in the incorrect phase and has the
incorrect Work Breakdown Structure (WBS) numbering. You need to move the section to
another phase of the project. You also need to ensure that the section reflects the correct
WBS numbering. What should you do?