You use Project Professional 2010 to manage a construction project. Different members of
the project team frequently modify a blueprint file. The file is saved in a Microsoft Office
SharePoint document library. You need to access the file from within the project schedule.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Add a hyperlink.

B.
Use the Links Between Projects tool.

C.
Use the Sync with Tasks List feature.

D.
Use the Save to SharePoint feature.