PrepAway - Latest Free Exam Questions & Answers

You need to assign the task to the resource without scheduling the task

You have an unscheduled, unassigned task in your Project Professional 2010 schedule. You
identify an available resource. You need to assign the task to the resource without
scheduling the task. What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Use the Replace feature in the Assign Resources dialog box.

B.
Use the Add Resources function.

C.
Use the Team Planner view.

D.
Use the Calendar view.


Leave a Reply