Normally, it would be essential to involve which of the following stakeholders in the initiation stage
of a project?

PrepAway - Latest Free Exam Questions & Answers

A.
System owners

B.
System users

C.
System designers

D.
System builders

Explanation:
System owners are the information systems (project) sponsors or chief advocates. They normally
are responsible for initiating and funding projects to develop, operate and maintain information
systems. System users are the individuals who use or are affected by the information system. Their
requirements are crucial in the testing stage of a project. System designers translate business
requirements and constraints into technical solutions. System builders construct the system based
on the specifications from the systems designers. In most cases, the designers and builders are
one and the same.