The activation of an enterprise’s business continuity plan should be based on predetermined criteria
that address the:

PrepAway - Latest Free Exam Questions & Answers

A.
duration of the outage.

B.
type of outage.

C.
probability of the outage.

D.
cause of the outage.

Explanation:
The initiation of a business continuity plan (action) should primarily be based on the maximum
period for which a business function can be disrupted before the disruption threatens the
achievement of organizational objectives.