Doing which of the following during peak production hours could result in unexpected downtime?

PrepAway - Latest Free Exam Questions & Answers

A.
Performing data migration or tape backup

B.
Performing preventive maintenance on electrical systems

C.
Promoting applications from development to the staging environment

D.
Replacing a failed power supply in the core router of the data center

Explanation:
Choices A and C are processing events which may impact performance, but would not cause
downtime. Enterprise-class routers have redundant hot-swappable power supplies, so replacing a
failed power supply should not be an issue. Preventive maintenanceactivities should be scheduled
for non-peak times of the day, and preferably during a maintenance window time period. A mishap
or incident caused by a maintenance worker could result in unplanned downtime.