When installing IBM Maximo Asset Management V7.5 without using the middleware installer to
install IBM WebSphere Application Server, which step must be taken for a successful installation?

PrepAway - Latest Free Exam Questions & Answers

A.
The JMS connection factory must be created in a special, separate cell connected to an IBM DB2
data store to provide a way for server failures to be recovered.

B.
The WebSphere Application Server must be configured to allow for remote execution and access
traffic in order for the installer to successful^ obtain the trust.p12 file using a remote file copy
method.

C.
JMS data stores must be created using a database (with a supported vendor: IBM, Oracle, or
Microsoft) in order to allow the manual configuration of the JMS resources to be successfully
completed.

D.
The trust.p12 keystore file must be copied from the WebSphere Application Server’s deployment
manager profile>/etc directory to a suitable location and be provided as an input to the installation
program