Which statement is true regarding a work order that results from a job plan?

Job plan’s responsibility can be assigned to a supervisor, crew, lead, and owner. Which statement is
true regarding a work order that results from a job plan?

PrepAway - Latest Free Exam Questions & Answers

A.
The values for supervisor, crew. lead, and owner from the job plan always carry over to the work
order regardless of the values for supervisor, crew, lead, and owner defined on the preventive
maintenance record.

B.
If the values for supervisor, crew, lead, and owner on the preventive maintenance record are
different compared to those on the job plan, the values on the preventive maintenance record take
the place of those on the job plan when copied to the work order.

C.
If the values for lead and owner are different on the preventive maintenance record compared to
those on the job plan, the values on the preventive maintenance record take the place of those on
the job plan when copied to the work order. Values for supervisor and crew come from the job plan.

D.
If the values for lead and owner are different on the preventive maintenance record compared to
those on the job plan, the values on the job plan take the place of those on the preventive
maintenance record when copied to the work order. Values for supervisor and crew come from the
preventive maintenance record.