A forecast for a preventive maintenance record has been generated. How can the forecast date be
adjusted from the Preventive Maintenance application?

PrepAway - Latest Free Exam Questions & Answers

A.
From the Forecast tab, select a forecast row, enter a value in the New Date field, click Save

B.
From the Select Action menu, select Generate Forecast, enter a value in the Forecast Days field,
click OK

C.
From the Frequency tab, select the Time Based Frequency tab, enter a value in the Frequency
field, click Save

D.
From the Frequency tab, select the Time Based Frequency tab, enter a value in the Extended Date
field, click Save