What are two ways an administrator can add an existing attribute to the Work Order Tracking
application? (Choose two.)
A.
Conditional Ul application > select WOTRACK, select the new attribute, click the Show button
B.
Database Configuration application > select WORKORDER object, select the new attribute, click
the Show button
C.
Application Designer application > under Select Action menu select the Add/Modify Attributes
option, add the new attribute to the canvas
D.
Application Designer application > select WOTRACK, drag and drop the appropriate control to the
canvas, configure the control properties to bind the new attribute
E.
Application Designer application > select WOTRACK application, export the presentation XML file,
make appropriate changes in the XML file, import the presentation XML file