The data field titled Reservation Type is used when planning material reservations from the Plans tab
of Work Order Tracking. Which statement is true?

A.
An automatic reservation is a request for materials that is not subject to a timeframe.
B.
An automatic reservation defines the processing of the reservation based on the date the
materials are required.
C.
An automatic reservation is a request for materials that is defined by the need for an item from a
specific vendor.
D.
An automatic reservation takes over the stock item reorder process and automatically generates
the purchase requisition.