Which of the following should be included in a Gantt chart to analyze a project schedule? (Select Three).

Which of the following should be included in a Gantt chart to analyze a project schedule? (Select Three).

PrepAway - Latest Free Exam Questions & Answers

A.
Risks

B.
Probability

C.
Cost analysis

D.
Start date

E.
Activity durations

F.
Finish date