Which of the following project components will have to be updated to reflect working with a new time zone loca

In an attempt to make a deadline, a North American project manager is able to procure emergency funding for additional people. The resources are located in Europe. Which of the following project components will have to be updated to reflect working with a new time zone location?

PrepAway - Latest Free Exam Questions & Answers

A.
Communication plan

B.
Risk management plan

C.
Work Breakdown Structure (WBS)

D.
Project scope statement