After final acceptance, which of the following would the project manager use to assess the strengths and weakn

After final acceptance, which of the following would the project manager use to assess the strengths and weaknesses of the project?

PrepAway - Latest Free Exam Questions & Answers

A.
Post-project review

B.
Transition plan

C.
Project kick-off meeting

D.
Quality analysis