PrepAway - Latest Free Exam Questions & Answers

The work breakdown structure (WBS) dictionary contains which of the following elements? (Select Three).

The work breakdown structure (WBS) dictionary contains which of the following elements? (Select Three).

PrepAway - Latest Free Exam Questions & Answers

A.
Identification of stakeholders

B.
Description of work processes and procedures

C.
Quality control processes

D.
Estimated calendar time of activities

E.
Required resources

F.
Risk response strategies


Leave a Reply