Which of the following actions should the project manager take FIRST?

A customer requests that the products quality be reduced to control its cost. Which of the following actions should the project manager take FIRST?

PrepAway - Latest Free Exam Questions & Answers

A.
Modify the project schedule.

B.
Obtain approval for the change.

C.
Reduce the amount of project resources to control costs.

D.
Modify the project budget.