The method of cost-estimating whereby the costs of the individual work packages are aggregated to form the ful

The method of cost-estimating whereby the costs of the individual work packages are aggregated to form the full cost-estimate is called:

PrepAway - Latest Free Exam Questions & Answers

A.
parametric estimating.

B.
bottom-up estimating.

C.
expert judgment.

D.
analogous estimating.