Which of the following methods should the project manager select to investigate?

The schedule estimates for a particular work package that is underway were not properly considered and the timescales are too tight. Which of the following methods should the project manager select to investigate?

PrepAway - Latest Free Exam Questions & Answers

A.
PDM

B.
SPI and SV

C.
CPM

D.
Issues log