A project manager is informed that material expenditures will increase. Which of the following documents should be referenced to address this increase?

PrepAway - Latest Free Exam Questions & Answers

A.
Work Breakdown Structure (WBS)

B.
Cost management plan

C.
Approved project charter

D.
Project scope document