All of the following should be detailed in the communications management plan EXCEPT:

All of the following should be detailed in the communications management plan EXCEPT:

PrepAway - Latest Free Exam Questions & Answers

A.
the person responsible for communicating the information.

B.
team member roles and responsibilities.

C.
team members that will receive the information.

D.
frequency of project team communications.