A team member reports that a system component they are working on causes the system to continually reboot. The project manager should record this in which of the following documents?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Quality management plan
B.
Communication plan
C.
Risk matrix
D.
Issue log