A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Estimate to completion
B.
Planned value
C.
Cost performance index
D.
Budget at completion