PrepAway - Latest Free Exam Questions & Answers

Which of the following is the expected duration for this scheduled activity?

Given the following information: Pessimistic estimate is 30 days Most Likely estimate is 15 days Optimistic estimate is 10 days. Which of the following is the expected duration for this scheduled activity?

PrepAway - Latest Free Exam Questions & Answers

A.
11 days

B.
17 days

C.
25 days

D.
29 days


Leave a Reply