Which risk response is most likely to involve contingency reserves?

A.
Acceptance
B.
shaie
C.
Mitigate
D.
Transfer
Explanation:
Acceptance is when no change to the project is made for a risk. A contingency can be set aside to offset the impact of the risk.
I choose A