A cost management plan is ____________.

A cost management plan is ____________.

PrepAway - Latest Free Exam Questions & Answers

A.
A Plan for describing how cost variances will be managed

B.
A subsidiary element of the project charter

C.
An input to the Estimate Costs process

D.
All of the above

Explanation:
cost management plan is a plan for describing how cost variances will be managed.