Of the following, which is the best source of information for your project?

If you are project manager for a Project and will need as many inputs to the initiation phase as possible. Of the following, which is the best source of information for your project?

PrepAway - Latest Free Exam Questions & Answers

A.
Historical information

B.
WBS

C.
Business plans

D.
RBS

Explanation:
Historical information is the best input of the choices available. B is incorrect since the WBS has not been created at this point of the project. C is incorrect since business plans are not a likely input to the initiation process

6 Comments on “Of the following, which is the best source of information for your project?

  1. me says:

    When comparing the terms; prevention; and inspection, the purpose of inspection in Perform Quality Control is to keep errors:

    a. Out of the process
    b. Out of the hands of the customer
    c. In a specified range of acceptable results
    d. In line with a measured degree of conformity

    The answer is: b




    0



    0
  2. me says:

    Which statement best describes the main difference between a matrix organization and a functional organization?

    a. Project team members usually report to two bosses in a matrix organization – the functional manager and the project manager.
    b. More people will be assigned to work full-time on projects in a functional organization that in a matrix organization.
    c. Project managers have more authority in a functional organization than they do in a matrix organization.
    d. Most companies have found that functional organization structures provide the most flexibility for managing projects.

    The answer is: a




    0



    0
  3. me says:

    Which Control Quality tool, previously known as an arrow diagram, is used with project scheduling methodologies such as PERT, CPM and PDM?

    a. Activity network diagram
    b. Tree diagram
    c. Affinitydiagram
    d. Matrixdiagram

    The answer is: a




    0



    0
  4. me says:

    What links Project Management Process Groups?

    a. The organization’s policies and procedures
    b. The outputs they produce
    c. Discreteorone-timeevents
    d. The tools used to support the project management information system

    The answer is: b




    0



    0
  5. me says:

    One of the tools and techniques used in the Develop Project Charter process is:

    a. analytical techniques
    b. expert judgment
    c. meetings
    d. change control tools

    The answer is: b