You are a project manager for a manufacturing firm . You discover a design error during a test production run on your latest project. Which of the following is the most likely response to this problem?

PrepAway - Latest Free Exam Questions & Answers

A.
Reduce the technical requirements so that the error Is no longer valid.

B.
Go forward with production, and ignore the error.

C.
Go forward with production, but inform the customer of the problem.

D.
Develop alternative solutions to address the error.

Explanation:
Best answer to this problem is to develop alternative solutions to address the design error. Reducing technical requirements might be an alternative solution, but it is not one you had implement without looking at all the alternatives. Ignoring the error and going forward with production will result in an unsatisfactory product for the customer.