A.
Initiating, Planning, Monitoring and Controlling, Executing, and Closing
B.
Initiating, Executing, Planning, Monitoring and Controlling, and Closing
C.
Initiating, Monitoring and Controlling, Planning, Executing, and Closing
D.
Initiating, Planning, Monitoring and Controlling, Executing, and Closing
Explanation:
Remember IPECC (Initiating, Planning, Executing, Monitoring and Controlling, and Closing).
While the Explanation shows correct order the Options are wrong.
0
0
Correct answer is A