Which of the following are input of close project process?

Which of the following are input of close project process?

PrepAway - Latest Free Exam Questions & Answers

A.
Project management plan

B.
Contract documentation

C.
Deliverables

D.
All of the above

Explanation:
All are inputs of close project process.