Which of the following are the outputs of Collect Requirements Process?
A.
Requirements documentation
B.
Requirements management plan
C.
The requirements tractability matrix
D.
All of the above
Explanation:
The outputs of Collect Requirements Process are: requirements documentation (stakeholder’s needs), the requirements management plan (how the requirements will be analyzed and documents), and the requirements traceability matrix (tracking of requirements throughout the project).