Lessons learned session should be held at what point in a project?

Lessons learned session should be held at what point in a project?

PrepAway - Latest Free Exam Questions & Answers

A.
At the project conclusion

B.
At key milestones

C.
When risk events occur

D.
When sponsor want

Explanation:
Although lessons learned should be held at project conclusion, they should be held throughout the project any time.