Which process must occur after a project manager has been assigned to the project?

A.
Collect Requirements
B.
Develop the project charter
C.
Develop the project statement of work
D.
Develop project closing document
Explanation:
The Collect Requirements process occurs during project planning. Other options occur during project initiation. Option D is associated with project closing. Collect Requirements is the best option.