Which process is not included in the Project Time Management process?

A.
Define Activities
B.
Sequence Activities
C.
Develop Schedule and Control Schedule
D.
Work breakdown structure (WBS)
Explanation:
Work breakdown structure (WBS) is not included in Project Time Management but all other options provided in Project Time Management.
I agree with the answer. D