Which process involves monitoring, measuring, and taking corrective action?

A.
Executing processes
B.
Planning processes
C.
Controlling processes
D.
Closing processes
Explanation:
Planning Processes: Approach to executing project. Executing processes: Coordinating people and other resources. Controlling Processes: Monitoring, measuring, and taking corrective action. Closing processes: Formal product acceptance and end of project.