Which process involves coordinating people and other resources to carry out a plan?

Which process involves coordinating people and other resources to carry out a plan?

PrepAway - Latest Free Exam Questions & Answers

A.
Executing processes

B.
Planning processes

C.
Controlling Processes

D.
Closing processes

Explanation:
Planning Processes :Approach to executing project. Executing processes :Coordinating people and other resources. Controlling Processes :Monitoring , measuring, and taking corrective action. Closing processes : Formal product acceptance and end of project.