You are project manager and working on gathering requirements and estimating for the project.
Which process group are you in?

A.
Planning
B.
Monitoring and Controlling
C.
Executing
D.
Initiating
Explanation:
In the Planning process requirements are fleshed out, stakeholders are identified, and estimates on project costs and time are made.