Which one of the following is being inadequately reported?

You are project manager and the monthly report to the client showed zero schedule variance. However, member of the team know that a milestone has been missed which will cause an overall delay to the project. Which one of the following is being inadequately reported?

PrepAway - Latest Free Exam Questions & Answers

A.
Communication plan variance

B.
Resource management plan

C.
Critical path status

D.
Risk analysis