Which one of the following comes first in the project plan?

A.
Scope Statement
B.
Quality Plan
C.
WBS
D.
Development Plan
Explanation:
Scope statement comes first in the project plan. Scope statement is the written statement of project. It contains: Project objectives, Project justification, Project deliverables