Which of the following would you send to the executive?

You are the project manager of a project .The senior executive of your company wants monthly schedule update of your project. Which of the following would you send to the executive?

PrepAway - Latest Free Exam Questions & Answers

A.
Milestone chart

B.
Time scaled network diagram

C.
Arrow activity diagram

D.
PERT chart